Construction of new Church Hill Water Tank should begin this month

March 8, 2017 8:15 am by

The construction of the new tank concrete foundation has been completed and construction of the tank walls is expected to start in March, 2017 and take about 6 months to complete.

PROJECT SCHEDULE:

  • New Tank Construction: December 2016 through September 2017
  • Demolish Existing Tank: October 2017 through December 2017
  • Upgrade to Electric Streetlight Substation: October 2017 through December 2017
  • Site Restoration and Final Landscaping: January 2018 through April 2018

— ∮∮∮ —